October 1, 2026
Walk the paved edge of Chastain Park north past the horse park and the tennis courts, and the trail keeps going under the tree canopy toward Roswell Road. Then it stops. The pavement ends at a four-lane stretch of Roswell Road, and the gravel entrance to Blue Heron Nature Preserve sits directly across the street, close enough to see and impossible to reach on foot without crossing traffic. Anyone who has made that walk in the last eight years has heard the gap described as temporary. The word never changed even as the calendar did.
That temporary label finally has something behind it. The City of Atlanta's transportation department now lists a project called Blueway Trail Planning, and for the first time since the idea was floated, there is an actual corridor drawn on a map linking Blue Heron, Sarah Smith Elementary School, and Chastain Park into the single connected green space that residents already treat it as on weekends.
Blue Heron broke ground on what it called the Blueway Trail Initiative in April 2018, with Atlanta City Council District 7 member Howard Shook, Atlanta's Park Commissioner Amy Phuong, and Park Pride Executive Director Michael Halicki on hand for the ceremony. The plan had two phases from the start. Phase 1 covered the preserve's own three parcels, a soft-trail loop through wetlands and woods along Nancy Creek. Phase 2 was the part that mattered to anyone outside the preserve's fence line: a connection west to Chastain Park and PATH400, and east toward the Atlanta BeltLine.
Phase 1 got built. Blue Heron raised more than $750,000 over three years, installed two bridges, and opened the finished three-mile Blueway Trail in January 2020, timed to the nonprofit's own 20th anniversary that spring. Phase 2 sat exactly where it started. A 2019 report on the fundraising milestone noted the Chastain and PATH400 link had no current timeline, and that sentence stayed true for years. At one point, the city's TSPLOST/Renew Atlanta bond program had earmarked $1.1 million for that exact connection. The current study is funded through a different program, the Moving Atlanta Forward bond, which shows how a short trail link can span more than one bond cycle before it reaches a concept design.
The difference is a feasibility and concept design study, funded this time through the Moving Atlanta Forward bond, with a completion target of spring or summer 2026. The study has already produced a preferred corridor, what the project documents call a fat line on the map, running between PATH400, Sarah Smith Elementary, Blue Heron, and Chastain Park. City planners are careful to note this isn't a final route. It shows where the trail could reasonably go based on topography and environmental impact, and the next phase of design work will narrow that band down to an actual alignment, including how close it comes to backyards and how it protects sensitive sections of the creek.
One decision has already been made, though, and it explains why this stretch of trail has been harder to finish than the flat, paved miles of PATH400 a half mile away. Planners are recommending a split trail at Blue Heron, with the bike path and the pedestrian path taking different routes to reach PATH400 rather than sharing one corridor. A combined trail, the study concluded, would compromise the character of the preserve and the environmental protections it was built around. That's a different problem than money or politics. It's a design constraint that comes from the fact that Blue Heron is a working wetland and wildlife habitat first, and a through-trail second, and the two uses don't automatically fit on the same six feet of tread.
Here's the loose timeline, worth keeping straight if you've heard some version of this story before:
| Year | Milestone |
|---|---|
| 2018 | Blueway Trail Initiative groundbreaking, Phase 1 begins |
| 2020 | Internal three-mile Blueway Trail completed, two bridges installed |
| 2019-2025 | Phase 2 link to Chastain and PATH400 had no fixed timeline |
| 2025 | PATH400's Wieuca-to-Loridans segment opens, one mile south of Blue Heron |
| 2026 | City feasibility study identifies a preferred corridor for the Blue Heron connection |
While the Blue Heron link was stalled, the trail system next door kept moving. Livable Buckhead cut the ribbon on PATH400's final major Buckhead segment on September 26, 2025, opening three-quarters of a mile of paved greenway between Wieuca Road and Loridans Drive. The centerpiece is the Mountain Way Common bridge, an 80-foot-high crossing built by C.W. Matthews Contracting that carries walkers and cyclists over the creek without touching Roswell Road at all. The segment cost $13.4 million and came with nearly 500 newly planted native trees along its shoulders.
Put that dollar figure next to Blue Heron's own $750,000 campaign and the contrast is worth sitting with. That money built three miles of natural trail inside the preserve, a little over $250,000 a mile. The PATH400 segment ran about $17.9 million a mile for three-quarters of a paved mile with a bridge. Paved, permitted, engineered trail through a residential corridor costs many times more per mile than a soft trail through land the preserve already owned, which is part of why the short gap between the two systems has taken longer to close than either finished piece did on its own.
The practical upshot for anyone near Sarah Smith Elementary is that the walk-to-school route no longer has to cross Roswell Road at that stretch, and Mountain Way Common's 8.6 acres of creekside woods are now reachable without a car. The next segment, running from Loridans Drive north to the Sandy Springs city line, is under construction now, with Sandy Springs' own 2.3-mile extension expected to finish by summer 2029.
None of the planning changes what Blue Heron already offers today, and the fall calendar is running on its usual rhythm. The preserve's Second Saturday Safari pairs a guided trail walk with a local expert each month, past sessions have included researchers from the Atlanta Coyote Society and a forest ecology walk led by Trees Atlanta, and the next one on the books is a Wildlife Photography session with the Atlanta School of Photography on October 10. Fall Break Camp runs for ages 4 to 8, a full day from 9 a.m. to 4 p.m. with no early drop-off or late pickup, and families can register for individual days or the whole week.
A few practical notes for anyone making the trip: the main entrance sits at 4055 Roswell Road NE, MARTA bus Route 5 stops at Roswell Road and Chastain Drive from either Lindbergh Center or Dunwoody Station, and pets need to stay leashed the way they would in any City of Atlanta park. The preserve also shares its grounds with the Atlanta Audubon Society and the Amphibian Foundation's field research center, which is part of why the environmental review on the new trail corridor is being taken as seriously as it is. This isn't a patch of grass waiting for a sidewalk. It's an active research site that happens to have a very popular walking loop running through it.
The gap across Roswell Road is still there for now. But for the first time since 2018, there's a drawn corridor, a funding source, and a stated design principle behind closing it, which is more than the neighborhood has had to go on for the better part of a decade.
If you spend your weekends on this stretch between Chastain and Blue Heron and you're curious what a fully connected trail network does to how a block like this holds its value, Catherine Newsome knows this corridor on foot, not just on paper, and is glad to talk through what she's seeing.
November 19, 2026
November 12, 2026
November 5, 2026
October 29, 2026
October 22, 2026
October 15, 2026
October 8, 2026
October 1, 2026
September 24, 2026
Whether you're buying or selling, Catherine Newsome is committed to guiding you through every step of the real estate process with integrity, passion, and personalized service. Let her help you find your dream home or sell your property for the best price—your goals are her priority!